Print
Version
FACING THE ENVIRONMENTAL CHALLENGE
Post-Tsunami Reconstruction in Indonesia
Emiel A.
Wegelin
Introduction
[1]
On December 26,
2004, an extremely strong earthquake (8.9 on the Richter scale) occurred
below the Indian Ocean, northwest of Sumatra Island. This earthquake,
which later caused a “tsunami” (ocean mega-wave), ravaged much of Aceh
and Nias in Indonesia, along with parts of Thailand, Sri Lanka,
Maldives, Bangladesh, Myanmar, and even some of Somalia’s eastern coast
in East Africa.
In Aceh and Nias,
the earthquake and tsunami damaged the larger part of Aceh’s coastal
areas, claiming heavy casualties and destroying infrastructure,
settlements, schools, health centers, shops, and public buildings. This
disaster deeply affected the social and economic conditions of the
population, severely dampening people’s sense of optimism.
According to the
government of Indonesia’s April 2005 Reconstruction Master Plan,
approximately 126,600 people were killed in Aceh and 93,600 people were
still missing, even before the second earthquake struck on March 28,
2005. The number of internally displaced persons (IDPs) in the province
was estimated at 514,100 people as of the middle of March. A total of
127,000 houses were completed destroyed and another 118,300 houses were
partially damaged. The total cost of the property destruction just in
Aceh alone, including housing and community infrastructure, was
estimated to be US$1.4 billion. The number of fatalities and displaced
persons in Nias (North Sumatra province) was initially more limited than
in Aceh, but this situation changed dramatically in the wake of the
earthquake of March 28, 2005, with its epicenter close to the islands of
Nias and Simeulue.
According to the
assessment carried out in May 2005 by the International Organization for
Migration together with the Indonesian Ministry of Public Works, a total
of 116,900 houses were damaged, of which 66,800 houses were completely
destroyed and an additional 14,200 houses sustained heavy damage in Aceh
province (with the balance sustaining light to medium damage), and
15,300 houses were completely destroyed and 19,400 houses were heavily
damaged (and another 60,000 houses sustained light to medium level
damage) on Nias island. Other government damage estimates arrived at
comparable numbers. On the basis of these damage assessments, combined
with enumeration of tsunami victims not requiring housing restoration
(those dead or resettled permanently elsewhere), the need for new
housing reconstruction was estimated at approximately 73,000 houses in
Aceh and more than 20,000 houses in Nias, while some 17,000 houses in
Aceh required repairs, and perhaps as many as 30,000 houses in Nias.
These estimates were subsequently revised, as many of the heavily
damaged houses were later determined to be unfit even for substantial
renovation.
The Indonesian
Government Response
The initial response
by the government of Indonesia, assisted by the international community,
was to come up with a damage assessment and reconstruction strategy
notes by the end of January 2005. A more detailed master plan for the
overall multi-sectoral reconstruction was adopted by Presidential Decree
in April 2005. A special agency, the Reconstruction and Rehabilitation
Agency (BRR) was established by the Indonesian government in May 2005 to
coordinate the overall reconstruction activities. The BRR’s main
functions are to provide leadership and direction to all of the
rebuilding efforts by national and international assistance agencies,
and to develop and implement the reconstruction master plan. The
Indonesian response strategy involved three overlapping phases:
emergency relief, rehabilitation, and reconstruction.
Housing Rehabilitation and
Reconstruction Strategy and Programs
Early in the
reconstruction process, the Indonesian government in its strategy notes
acknowledged the pivotal importance of rebuilding housing as part of the
overall redevelopment strategy. The government’s approach to rebuilding
housing embraced rehabilitation and reconstruction efforts in shelter
and community infrastructure by the surviving victims themselves in
the location where they lived before the Tsunami, and the need to
support these community efforts as the core approach to
government and international community support. Indonesia’s
Reconstruction Master Plan set two core standards for tsunami victim
household support: 1) that each surviving household would be entitled to
grant funds to rebuild their houses, with amounts of about US$3,000 per
house if it needed to be rebuilt from scratch, and 2) about US$1,000 for
damaged houses that could still be renovated. Grant funds also were
allocated for repair and reconstruction of community infrastructure.
On the basis of
these grant fund commitments, a housing reconstruction program for
85,000 new houses and 17,000 houses to be renovated was planned at a
total price tag of US$280 million (not including community
infrastructure), to be carried out over a period of three to four
years. Given the generous financial assistance pledges for post-tsunami
reconstruction coming from international donors, the Indonesian
government believed that sufficient resources would be available to
support the housing reconstruction program.
Issues in Implementing the
Reconstruction Strategy
When the housing
reconstruction strategy was quickly put together under great time
pressure, the Indonesian government was very well aware that many
operational problems would occur during its implementation, but decided
to go ahead nevertheless. During the subsequent implementation process,
problems were addressed in a learning-by-doing fashion. Some of these
challenges included:
a)
Identifying the surviving victim households and determining their grant
entitlements:
Two areas of concern were the most difficult: 1) preventing
“double-counting” because many victims registered for financial aid in
more than one community; and 2) fine-tuning the grant entitlements, such
as: i) what to do with the numerous part-surviving households, including
sole surviving children? ii) what to do with the large numbers of
tenants who were renting their housing before the tsunami disaster,
rather than owning their houses? iii) how to determine the appropriate
amount of the grant for housing renovation based on the actual degree of
damage incurred?
b)
The
nature of the dominant community-driven reconstruction approach: Many
preparatory planning and organizational steps are necessary at the
community level before people can begin rebuilding their houses, and
this takes considerable time; some parties therefore thought a huge
contractor-driven approach would work more rapidly and efficiently than
a community-based process, despite the significant risks of oversupply,
price escalation, lack of quality controls, and corruption.
c)
Land issues:
What to do with the many households who did not own legal title to the
land that they had lived on before? What to do with tsunami victims
unable to rebuild on the land that they previously occupied because it
is now submerged underwater as a result of geological changes?
d)
Spatial planning and environmental issues:
Was it reasonable to let people rebuild in their pre-tsunami location,
even in the case of central town areas that were totally destroyed
(sizeable parts of the towns of Banda Aceh, Meulaboh, Sigli, Gunung
Sitoli, and Sinabang), especially where there were obvious alternative
areas for major reconstruction? What should be arranged for tsunami
victims who had formerly been living in locations that were no longer
environmentally safe or desirable to rebuild?
e)
Linkages to infrastructure beyond the community level:
Funding for community level “micro-infrastructure” reconstruction was
generally included in the housing support programs, but there was still
a major gap, particularly in the larger urban areas that needed much
more substantial investment in rebuilding infrastructure since resources
of this nature and magnitude were not part of the community-based
housing reconstruction effort, but still were vitally necessary for the
overall success of the housing strategy, where would these funds come
from?
f)
Issues related to quality of housing and availability of building
materials:
While it was generally agreed that the quality of both the newly built
and the renovated houses should be higher than what people lived in
before the tsunami, including a much higher level of earthquake
resistance, these objectives, often seemed too ambitious within the
financial constraints of the overall grant budget; with regard to
building materials, there was an obvious concern about potential
scarcity and inflationary price pressures generated by the massive
rebuilding efforts. In addition, there was a concern that only
environmentally acceptable and legally procured building materials
(given the growing need to prevent illegal logging) should be used in
reconstruction activities, but that such a policy could further limit
supplies and drive up prices.
g)
Temporary Shelter:
Once it became clear that resolving the above issues would take
considerable time, new issues surfaced concerning what to do with the
substantial group of displaced households who were living in tents, in
temporary barracks, and with other families?
h)
Programming and Coordination Issues:
This had
two major dimensions: a)
how to
translate the generous national and international pledges of financial
support into operational projects and programs, and b) how to ensure
that
the more
than 80 national and international non-governmental organizations
(NGOs), international assistance agencies, and government departments
intending to support the community-based housing rebuilding efforts
would all work together in accordance with the Reconstruction Master
Plan’s approach and standards over a wide geographical area, and not
duplicate one another’s actions.
i)
Very Restricted Capacities to Manage and Implement the Housing
Reconstruction Program.
The tsunami and the
two earthquakes combined not only
resulted
in enormous human suffering, but they also decimated the capacity of
local and provincial governments to provide routine public services.
Most of the land ownership records were destroyed, as was a great deal
of the infrastructure. Many of the public and private support agencies
involved, NGOs in particular, were far more geared to maintaining
emergency operations and providing emergency assistance. Very few
personnel had any professional experience or capability in terms of
housing reconstruction.
All of these
important, complicated, and at times delicate policy and management
issues had to be addressed professionally and equitably, all at the same
time, in a high-pressure environment characterized by:
a)
A great impatience with the perceived slow pace of reconstruction
as against the obvious humanitarian needs, and in the wake of quick and
generous pledges for support. This frustration with the relatively slow
pace of progress in the early stages led to quite unrealistic
reconstruction time frames of three to four years.
b)
The actual capacity to address such a highly ambitious rebuilding
agenda would have been quite limited at the best of times, and, as noted
above, was even more so regarding segments of the local and provincial
governments, because much of their human resources were wiped out by the
tsunami.
c)
An ongoing civil war in Aceh Province between the Indonesian
government and the Free Aceh Movement, with a very strong military
presence in Aceh province, and a resulting phase 5 (the highest, later
reduced to 4) security status seriously restricting movement of support
workers.
Resolution
As noted above, all
of these issues had to be resolved in a quick learning-by-doing fashion,
in keeping with the spirit of the community-based reconstruction
approach and the fair allocation of entitlement grants. The role of
Indonesia’s Reconstruction and Rehabilitation Agency (BRR) in managing
and coordinating the entire process, issuing policy implementation
guidelines, and strengthening workforce capacities, turned out to be
very demanding.
At the time of
writing (early November 2005) most of the above issues have been or are
being resolved, and the predominantly community-driven housing
reconstruction program has assumed operational momentum with about
15,000 houses expected to have been completed or under construction by
the end of 2005. Outstanding issues are being resolved in favor of
reinstating the tsunami victims in as broad terms as possible, even if
such an inclusive approach takes priority over broader technical
considerations of efficient land allocation, land-use, and
infrastructure planning. Further examples of approaches taken by BRR
and its many national and international reconstruction partners to
resolve outstanding issues are discussed below.
‘Zonation’ and spatial planning
Considering the risk
of another tsunami, and the various geological changes that created new
and different tidal levels in the victims’ villages of origin, an
initial government policy proposed that victims’ housing reconstruction
should not occur within a demarcated zone from the new shoreline
(variously identified as between 300 and 1,000 meters). It became
readily apparent over time, however, that such a guideline was unduly
rigid and practically unenforceable. In view of this belated
recognition, the strict shoreline “no-build zone” policy was abandoned
and replaced by softer guidelines. The new policy simply informed
communities and their support partners that, while rebuilding housing at
the original location was the generally preferred option, this desired
outcome should be balanced against the substantial risk of future
flooding and the need for adequate tsunami protection, such as emergency
exit pathways. In many cases this led villagers to collectively decide
in favor of relocating their villages, land availability permitting,
farther away from the new shoreline, or at least to plan for safe
passage as part of the basic redesign of the village layout.
In urban areas in
which sizeable sections of the town centers had been completely
demolished by the tsunami, there was a strong initial preoccupation with
completely replanning and redeveloping those areas (possibly at the
expense of the return of all pre-tsunami residents), and an initial
restriction against victim families rebuilding their houses in damaged
areas. As there was a very strong grassroots movement insisting that
the national government’s reconstruction policy be fully implemented,
this prohibition was subsequently lifted and communities were allowed to
rebuild housing in damaged areas where their houses had previously been
located. The winning argument was that the post-tsunami crisis should
not be used as a convenient justification for “urban renewal”, but that
reinstatement of residents at the site of their former houses should
take precedence, taking into consideration requirements for improved
safeguards against flooding and earthquake risks.
Given the geological
changes that have occurred, adequate flood protection will require
massive investments in sea-walls and escape routes in many areas, while
the quality of individual houses will have to be rebuilt at higher
earthquake resistance levels than the destroyed pre-tsunami housing
stock. Such issues are reviewed and resolved on an area-by-area basis
at the community level, which in most cases is the best method for
reaching such participatory decisions. However, the Indonesian
Government also recognizes that in some seriously affected and now
low-lying areas with high pre-tsunami population densities, a
substantial infrastructure investment in protective structures and
mechanisms is essential.
Housing Entitlements for Pre-Tsunami
Renters
In some urban areas,
the proportion of renter households before the tsunami was as high as 20
percent. Because initially there were no policy guidelines about
entitlement grants for renter households, they tended to be excluded
from community-based reconstruction planning, which mainly involved
house owners. To overcome this disparity the BRR prepared new
guidelines for communities and reconstruction partner agencies that
included financial support for and participation by tenants. These
policy guidelines were introduced after a series of public debates on
earlier drafts, and they basically confirmed the principles of housing
reinstatement and entitlement grants for former renters. They also
provided for a number of practical options on how these principles could
be realized either within renters’ former communities or in other
locations. The guidelines enable former renters to participate in the
community reconstruction planning process with a legitimate claim
comparable to property owners. These new guidelines also included
operational guidance for NGOs and other reconstruction partners
regarding effective implementation.
Land Acquisition and Tenure Provision
for Victims Who Lost Their Land
Approximately 30,000
victim households in Aceh were unable to rebuild houses on the land they
owned before the tsunami, as a result of the geological changes, even
with the above-noted sea/flooding protection measures. In some cases
the original village location is now permanently sub-merged by several
meters of sea water.
The BRR, in
agreement with the provincial governments, issued policy
guidelines-of-last resort concerning acquisition of replacement land and
provision for land tenure in such cases. The basic strategy gives
priority for reinstatement on the original land wherever possible, with
resettlement on other lands only in cases where the original land was
physically unsuitable for reconstruction. In the guidelines the
government has, however, recognized that the affected victims should not
be hit doubly by inevitable loss of land such as by the above
submergence, and that the government has a responsibility to assist
through land acquisition. The principal agent to do so under the law is
the local government. The guidelines provide for a land acquisition
cost-sharing mechanism between BRR and the provincial government in
appropriate and well-defined cases. The guidelines provide for several
land tenure options to be applied by local governments, communities, and
reconstruction implementation partner agencies.
Temporary Housing
After the tsunami,
people who lost their housing were initially given temporary shelter in
tents, emergency barracks, and with host families. These arrangements
were intended to last for no more than six months. This relatively
brief time frame turned out to be inadequate, given the length of time
it took to deal with all of the legal, technical, financial, and
coordination issues involved in large-scale reconstruction. In
recognition of the need to extend the time for which temporary shelter
accommodation will be required, new guidelines were issued for
communities and reconstruction partners regarding short-term housing,
directed at:
a)
improving the quality of existing barracks;
b)
adding new barracks close to locations of origin or near future
permanent rebuilding sites;
c)
replacement of dilapidated tents, preferably near future
rebuilding sites or original locations;
d)
extending financial compensation to host families, and providing
housing expansion and improvement grants to host families.
The BRR guidelines
also reconfirm to the tsunami victims that extending and improving
temporary shelter solutions will not detract from the financial support
for and the entitlement commitments to provide permanent housing and
community infrastructure.
Coordination of Reconstruction Actions
Coordination of the
reconstruction support efforts by the various government departments and
the more than 80 national and international NGOs and other donor support
agencies has not been an easy task for the BRR. This task was made even
more difficult due to the BRR’s resource and personnel constraints, and
because of the community-based reconstruction approach, with which many
support agencies had no prior experience. The BRR is attempting to
strengthen the existing shelter coordination mechanisms established
during the emergency relief period, drawing lessons from its recent
experience with the initial reconstruction activities.
A weekly Shelter
Coordination Working group meeting of all involved agencies is conducted
under joint provincial government and BRR sponsorship with an active
UN-Habitat support secretariat to review outstanding and emerging
issues. This forum also acts as a sounding board for review of draft
BRR policy guidelines.
In addition, the BRR
has mandated that all partner agencies submit reconstruction proposals
in a common format, to be endorsed and approved through common
procedures. The BRR also requires partner agencies to frequently submit
progress reports with detailed data for the purpose of tracking
implementation successes and overcoming obstacles. As the set of
implementation guidelines becomes more complete, the BRR will use both
its guidelines and partner agency progress reports for the purpose of
monitoring compliance.
Conclusion
Looking back over
these past 10-11 months, the author’s view is that it is miraculous how
much progress has, in fact, been made against staggering odds in dealing
with the above issues, and despite the undoubted shortcomings in
specific areas. One success factor has been the leadership by the
Indonesian government in formulating policy and strategy through the
Reconstruction Master Plan, and in coordinating reconstruction
implementation by the BRR, thus providing a practical operational
framework for support actions by all public, private, and community
stakeholders within Indonesia and from all over the world.
In August 2005, the
Indonesian government negotiated a peace agreement with the Free Aceh
Movement, which has now been ratified and is being implemented
step-by-step. Peace in Aceh has been of paramount importance in
enabling the reconstruction process to move forward, and both sides
deserve praise for putting aside their political differences at a time
of environmental crisis and human tragedy.
The recent peace
agreement holds out the promise of an accelerated reconstruction effort
in Aceh in 2006 and beyond, though many operational capacity constraints
will continue to limit progress. As reconstruction proceeds, a more
realistic appreciation of those constraints will hopefully emerge. This
new pragmatic perspective can lead to a more balanced view of what can
reasonably be accomplished within a relatively brief period of time,
with complete resolution of the housing reconstruction agenda possibly
to be achieved within five years after the tsunami and two earthquakes
initially occurred.
Emiel A. Wegelin
is Vice Chair of Global Urban Development, Director of UrbAct in
Rotterdam, Netherlands, and former Coordinator of the United
Nations/World Bank Urban Management Program (UMP). Dr. Wegelin’s books
include
Housing the Urban Poor, Urban Low-Income Housing and Development,
New Approaches in Urban Services Delivery, and Governing
Cities and Shelter Upgrading for the Urban Poor. He served as member
of the United Nations Human Settlements Program (UN-Habitat) support
team aiding post-Tsunami reconstruction in Indonesia.
[1]
The author has been part of the
UN-Habitat support team for shelter reconstruction in Aceh and Nias
intermittently during February-September 2005. The views expressed
in this article are his own and are not necessarily held by
UN-Habitat.
Return to top |